The project has two main parts ;
Ataköy - Çorlu (96 km long "duct",
12 km long "armoured" and 12
tubes coaxial cable laying works) and
Çorlu - Kapikule and Tahtakale - Ataköy
(60 km long "duct", 84 km long
"armoured" and 4 and 6 tubes
coaxial cable laying works).
The system shall operate with 3,600 channel
capacity, then shall be raised to 7,680
channel (565 Mbit/s) digital system capacity.